Paver Base Preparation
A wavy paver patio was wavy underneath before the first paver went down.
The layer cake, bottom to top
A paver installation is a layer cake: compacted native soil at the bottom, then compacted road base (deeper for driveways than patios), then a thin screeded bedding layer of coarse sand, then the pavers, then joint sand locking it all together. Every layer exists to spread loads and manage water, and the base layer is where nearly all failures start.
For foot traffic, the base typically runs 4 to 6 inches; for vehicles, 8 to 12. In clay soil — most of the valley — deeper is safer, because the base is also your buffer against the clay's seasonal movement.
Compaction in lifts, again
Just like under a concrete slab, base material has to go in a few inches at a time with each lift compacted before the next. A plate compactor only densifies the top few inches of loose material — dump it all at once and the bottom stays loose, and loose base is future ruts with a schedule.
The bedding sand layer is the opposite: it is screeded flat and NOT compacted before the pavers go down — the pavers get vibrated into it at the end. Crews that compact the bedding layer or use it thick to hide sloppy base grading are building waves into the surface.
What to ask any paver bidder
How deep is the excavation? What base material, how thick, compacted in how many lifts? How thick is the bedding layer? Real answers are numbers. Ours are on the written quote.